Update from Jim Gruenewald:

The Trustees met again Tuesday night to discuss the state of the lake.

First decision. The possibility of a small lake dredge was quashed. What initially looked like a good opportunity for the subdivision had turned into a major financial decision, not appropriate at this time.

Second decision. The Trustees decided to send letters to the remaining lakeside homeowners whose wall projects have stalled, informing them of a deadline to have their wall work completed. It is their responsibility to speak with their contractor(s).

Third decision. Our current landscaping company has failed to provide an estimate to treat, cut and remove the terrestrial weeds which have grown around the lake perimeter. We are contacting other companies for the work.

As of late yesterday, Jerry Parrish, contractor for most of the walls, responded to text by me and email from Sandy Baker, claiming his work to start again next week.